Add a Contract Time Limit

How to add Working Days, Calendar Days, or Completion Date to track your project's construction schedule.

Updated over a week ago

Overview

Background

Pegasus supports contract Time Limit tracking, time limit extensions or reductions via Change Order, Reporting Analytics, and Liquidated Damages. Contract Time Limit configurations include: Calendar Days, Completion Date, and Working Days.

NOTE: The Time Limits feature is optional set for contract and not required in order to Approve your project's Contract in Pegasus. If Time Limits are not added to a Contract you will not be able to modify time limits via Change Order or view Time Limit Analytics for you project.

Definitions

  • A calendar days schedule calculates the project's duration based on the entire calendar, encompassing weekends, public holidays, and any other non-working periods. This method focuses on the overall time elapsed from the project's commencement to its completion, irrespective of whether work is performed on a specific day or not.

  • The date when a contractor needs to be complete at project's job site.

  • A working days schedule is a project schedule that takes into account only the designated working days for calculating the project's duration. Non-working days, such as weekends, public holidays, or any other agreed-upon non-working periods, are excluded from the project timeline. This method is primarily concerned with the actual days when labor and resources are actively engaged in the project.

  • Funds covering the costs for each day the project continues past the agreed-upon date of completion. These funds are typically deducted from what the owner owes the contractor for work performed.

Permissions

The Time Limit feature requires Manager permissions to add, edit, or remove time limits on a given project.

Now that we have an understanding of how each Time Limit is defined and works in Pegasus we can continue below for steps on creating a Contract Time Limit.


How to Add a Time Limit to a Contract

Calendar Days

The Contract Time Limit is an optional feature in Pegasus and is not required for contract setup and Approval.

  1. Once you have a Draft Contract created, navigate to the Contract page and Open the contract.

  2. Locate the Contract Schedule section and select the Create button.

  3. Select the Schedule Type (Working Days, Calendar Days, or Completion Date) from the dropdown menu.

Contract Schedule

Completion Date

The Contract Time Limit is an optional feature in Pegasus and is not required for contract setup and Approval.

  1. Once you have a Draft Contract created, navigate to the Contract page and Open the contract.

  2. Locate the Contract Schedule section and select the Create button.

  3. Select the Schedule Type (Working Days, Calendar Days, or Completion Date) from the dropdown menu.

Contract Schedule

Working Days

Setup

Tracking

  1. Once you have a Draft Contract created, navigate to the Contract page and Open the contract.

  2. Locate the Contract Schedule section and select the Create button.

  3. Select the Schedule Type (Working Days, Calendar Days, or Completion Date) from the dropdown menu.

Contract Schedule

Liquidated Damages

How to Remove a Time Limit from a Contract

Did this answer your question?