The Contracts Tab on the Analytics page contains 5 sections (in order from top of page):
Info Cards Section
The Info Cards section displays infographic cards containing quick contract information including:
Contract Amount Paid: The total amount invoiced or payed for you project. This card totals all Payments created in Pegasus against the Total Contract Amount.
Amount Installed: The total amount installed card includes all Pay Items totaled from Field Reports and displays the total dollar amount against the Total Contract Amount.
Remaining Funds: This card displays the Remaining Funds or Contract Amount (Total Contract Amount - Contract Amount Paid = Remaining Funds).
Items Over Budget: Displays the number of pay items exceeding their respective bid amount. Also displays the total dollar amount over bid amount across all surplus items.
Quantity Chart
The Quantity Chart section displays all Pay Items belonging to a contract on your project. You can view how much has been installed for each item compared to the total bid amount as well as view the remaining amount for each item until completed.
Production Chart
The Production Chart displays the percentage of the contract installed over time. You can set time date ranges and time parameters such as Day, Week, Month, and Year views.
Itemized Sheet
The Itemized Sheet section displays individual and cumulative totals for each bid item or pay item in the contract belonging to your project. This is a useful section and heavily used by most in Pegasus.
Weekly Snapshot
The Weekly Snapshot section provides you with historical data analysis into the status of your contract during a specified week. It will also display the percentage complete that week, percentage completed to date, cost this week and previous, and cost to date.
Continue reading on for in depth how-to guides for each section in the Contract Tab on the Analytics page: